On July 16, the first batch of battery-grade lithium carbonate products from the Yongshan Lithium Phase II project (EPC services provided by Sunrise SNE), officially rolled off the production line. Testing indicates that all quality indicators meet the required standards, with purity exceeding 99.8%.
Since the announcement of the Phase II (EPC services provided by Sunrise SNE) project construction commencement in April 2023, it has taken only 5 months to complete the topping-out of 22 individual buildings, 8 months to finish installing all main equipment, and 11 months for the pyrometallurgical section to be ready for ignition.